Concrete Work & Reinforcement
Electric Columns Installation
Overview
Mobilization date on November 2018, with an anticipated completion date by end of 2022.
-
EXCAVATION OF ROADS100%
-
GEO-GRID WALLS100%
-
SEWAGE NETWORK100%
-
ELECTRIC POLES100%
-
WATER SUPPLY100%
-
FIBER OPTICS NETWORK100%
Project progress
December 2020
Concrete Work & Reinforcement
Entrance Lot Excavation
Construction of First Electric Room
October 2020
Excavation Under Retaining Wall
Plumbing Work and Fill
Construction of First Electric Room
July 2020
Barrier walls excavation
Safety walls excavation
Plumbing Work (Trench Excavation, Manholes Fixation & Pipes Laying)
April 2020
Wall footing excavation with concrete work
Safety walls excavation
Finalization of the mock-up road